Transportation/Traffic
Funded FY27–31

Transportation Projects (Minor)

Project CPT009 · Public Works

Also identified in the budget as “Transportation Projects(Minor)” (project code CPT009).

Cost & funding
Five-year planned cost
$600,000
Where the money comes from
  • Special Revenue Funds$600,000
Specifically
  • Transportation Impact Fees$600,000

    Fees paid by new development to offset its traffic impact. Can only fund transportation projects in the City's nexus study.

Source: FY 2026–27 CIP, Fund 351 appropriation.

Funding pathway

Funding pathway has not been mapped for this project. The project may be in a study phase, or its scope and cost are not yet defined.

Category
Capital Improvement Plan
Department
Public Works
Spent FY 2023–25
$147,743
Budget labels for this project

Sources: City of Menlo Park OpenGov CIP detail, project code CPT009; resident-facing name shown here is “Transportation Projects (Minor)”. The OpenGov summary label is “Transportation Projects(Minor)”. Budget worksheet labeled “Transportation Projects (Minor)”.

$600K
Planned spending, FY 2027–31
The City has not published a total lifetime cost estimate for this project, so there is no funding gap to show. The figure above is what the five-year plan budgets.
Show source

The funding gap is the estimated lifetime cost minus all funding that has not been lost, added up from the funding sources listed below. Year-by-year figures come from the City's adopted five-year capital plan.

Who is paying

Funding sources

The City has not recorded specific outside funding sources for this project. Projects can still be paid for from general capital funds even when no individual grant or source is listed here.

No funding sources are recorded for this project yet.

Spending

Spending by year

Past years are recorded actuals from the City's general ledger. FY 2026 is the adopted current-year budget. FY 2027 through FY 2031 is what the five-year Capital Improvement Plan proposes to spend.

FY 23$1,609
FY 24$86,803
FY 25$59,331
FY 29$200,000
FY 30$200,000
FY 31$200,000
Spent Current year (adopted) Planned
Where the money went, line by line
YearFundCategoryAmount
FY 23Special Revenue FundsServices$1,609
FY 24Capital Project FundsServices$53,922
FY 24Special Revenue FundsServices$30,000
FY 24Capital Project FundsSalaries and Wages$1,935
FY 24Capital Project FundsFringe Benefits$946
FY 25Capital Project FundsServices$59,223
FY 25Capital Project FundsSalaries and Wages$81
FY 25Capital Project FundsFringe Benefits$27
Show source

Past years are summed from gl_transactions for this project. FY 2026 is the adopted current-year budget for the project. FY 2027 through FY 2031 is what the City's adopted five-year CIP proposes to spend, taken from cip_projects.

How decisions were made

Council actions

No Council actions are linked to CPT009 yet. As decisions tied to this project are added to the database, they will appear here.