Every budget, capital-project, and grant decision the City Council has taken that we have on record, newest first. Expand any item to see what staff recommended, how the Council voted, and the source document.

  1. approve

    Council approved updated Middle Ave Caltrain Crossing design based on Caltrain comments

    Details

    Approved a redesign shifting the tunnel south, lowering it about 3 feet to facilitate construction without interrupting railroad operations, and extending the tunnel length to place the ramps out of Caltrain's right-of-way. Council also requested Caltrain consider an "uncovered" segment of the tunnel in the part of Caltrain's right-of-way not currently needed for active train service.

  2. approve

    Council approved modification to PD permit for 700-800 El Camino Real to facilitate Middle Ave ramp acquisition

    Details

    Approved a modification to the planned development permit for 700-800 El Camino Real to facilitate the purchase of a portion of that property for the ramps for the crossing, as recommended by the Planning Commission on May 1, 2023.

  3. approve

    Council certified Middle Ave project environmental document and approved 30% project plans

    Details

    Council certified the addendum to the El Camino Real and Downtown specific plan EIR and approved the 30% project plans. This was the CEQA clearance step; NEPA clearance was still pending as of the May 2024 MOU.

  4. approve

    City Council selected preferred alternative for Middle Ave Caltrain Crossing

    Details

    Council unanimously passed a motion to select an undercrossing approximately 10-12 feet below the street/plaza elevation that generally aligns with a proposed raised crosswalk on Alma Street and is slightly offset from the plaza at 500 El Camino Real (Stanford's Middle Plaza development).

    Vote: unanimous